The newly constructed pedestrian bridge, which opened in March 2008, provides direct access from Stirling Terrace to the waterfront. 

The Waterfront at Albany project is moving ahead with the following dates outlining the work which will take place in delivering the project to the Albany community:

    • Pedestrian Bridge officially opened to the public - March 2008
    • Civil works Stage 1 (remediation and subdivision of land) – completed November 2008
    • Construction of Entertainment Centre commenced – late 2008
    • Commencement of civil works on Stage 2 - mid 2009
    • Completion of civil works – late 2010
    • Completion of Entertainment Centre – late 2010
    • Stage 1 harbour pens constructed and available for public use – 2011
    • Completion of hotel site – 2010/2011